The project headquarters of the Park held a mobilization meeting for 200 days
Time:2017-06-04   Read:583second  

In May 31, 2017, the project coordination meeting of the project headquarters of the park was held every Wednesday. At the meeting, Gao Minglin, deputy general manager of the company, made a big mobilization for 200 days.
At present, the construction work of most sections of the park project is drawing to an end, and the work focus of each section is gradually shifted to the project installation.
Engineering installation is the most important part of chemical project construction, and its installation quality and schedule will directly affect the successful operation of the project. Therefore, the project installation management, control is very strict, requiring project construction personnel more investment, more careful, more professional. In accordance with the requirements of the company, adhere to the idea is not relaxed, the target is not shaken, standards are not reduced, action is not slow, to ensure that the end of 2017 with mechanical test conditions. To this end, in June 1, 2017 for "big 200 days" of the starting point, with 200 days for the deadline to ensure that the company handed out a satisfactory answer.
The meeting was presided over by Gao Minglin, deputy general manager of the company, and all the staff participated in the project construction. Gao Minglin first elaborated the park project construction present situation, take the project construction time as the main line, analyzed each section of the urgent need to solve the problem, combed the work task in 200 days, the key point, needs to control the detail. Gao Minglin, from the actual situation of the project construction, the project construction personnel put forward specific requirements, both technical requirements, there are management requirements, the ultimate goal is to ensure that the project completed on schedule with high quality.
Gao Minglin hopes to participate in the construction of the park project each person, can be promoted in the project construction, realize the ideal of life.
After the meeting, the project construction staff immediately entered the tense work, according to the big 200 days meeting requirements, itemized task decomposition. Everyone expressed the determination and confidence to complete the 200 day task, complete the high quality construction of the park project, and ensure the project to drive as scheduled.

CONTACT US

Anhui Province, Fuyang City, Fukang Road No. 1

0558-2368015 2368080

haoyuanweb@163.com

皖公网安备 34120002001531号

Message:
Name:
Telephone:
mailbox:
Technology supporter: Haoyuan Group Information Center
Technology supporter: Haoyuan Group Information Center
T
O
P