Recently, from the Fuyang coal based new materials Industrial Park project headquarters was informed that the park project is stepping up equipment installation, according to plan to drive test run in April 2018.
Fuyang coal based new material industrial park is located in Yingdong Town, Yingdong district. It is one of the key projects under construction in the city. It is an important platform to promote the rapid development of the chemical pillar industry in the city. The construction of the park follows the high end and diversification of the product, industrial circulation and chain operation. The technology is modernized and high-tech, and the production is safe and green. Constructing regional core, providing heat source and gas source to the whole park, forming the ecological balance of various materials and energy in the chemical industry system". Achieve energy cascade utilization, recycling, sustainable development.
The project under construction is the first phase of Ho yuan company, namely, an annual output of 260 thousand tons of styrene and 60 thousand tons of ethylene oxide and related projects. The project is the first project of Fuyang Industrial Park of coal based new materials, is an important move to the firm "excellent fertilizer, expansion of the transformation of leap development. The total investment of the project was 3 billion 780 million yuan, and construction was started in August 19, 2016.
"In order to better serve the project construction, ensure project construction process control, from the gasification framework piling day project personnel with the construction unit 24 hour shifts, the whole process of tracking inspection of the construction process, construction procedure, construction quality. During the concrete pouring, the project personnel carry out on-site supervision, to ensure the quality of casting and vibration. All the project staff will come to work at 7:40, work after lunch, and be home at 9 in the evening. In order to ensure the project construction plan and quality, everyone is very hard." Assistant General Manager Zhang Chao said.
At present, the civil engineering construction of the main part of the park project has been completed in full, with equipment installation conditions. The coal storage silo project, coal transportation and coal unloading system, supporting the Zhanqiao Waterworks Project, supporting the sewage treatment project and other supporting projects are under construction, is expected by the end of November will be the end of all civil, with equipment installation conditions.
All the equipments and equipments in the project have been fully delivered to 90%. The equipment in the purification section is expected to arrive in September 20th, with an annual output of 260 thousand tons. The styrene equipments are arriving in succession and are expected to arrive in the middle of November.
In the installation of equipment, the spare parts section, cold box, equipment installation and piping have all been finished in the project, and the pressure test is carried out in September. The outdoor facilities are all in place and piping of outdoor equipment is being carried out. Air compressor, supercharger, steam turbine and other indoor equipment is being installed; boiler section two, 260 tons per hour steam single boiler has been installed all over, hydraulic test has been completed, construction of furnace is under construction. Boiler electric bag dust removal, flue gas desulfurization, chimney, ash storage under construction, piping work is orderly, the electrical and instrument installation is in full swing; gasification section supporting static equipment, operation of equipment have all arrived at the scene in the ongoing pipeline installation unit, steel cap structure will be expected around September 20th. Fully vertically separated, the overall construction progress; the purification equipment has arrived the post transformation is completed, and in 90%, prefabricated pipe work is being carried out; the Rectisol section of the main equipment in place all the ongoing piping prefabrication. Other sections of the equipment are also arriving, installation, the scene of a busy scene.
In order to ensure the duration and quality of the project, the project Department of the park has put pressure on itself and put forward a proposal for 200 days' work. Ensure the quality of the project, ensure the safety of the construction, and orderly progress of the project, is the focus of work for 200 days.
"Although the hot weather in July, have an impact on the progress of the project, in August for half a month of rainy weather, the construction progress has lagged behind, but according to the overall progress of the project, as long as the post installation, increase the piping installation personnel, working overtime to promote, according to the project plan completed in April 2018 to drive no problem." Said Zhang Chao confidently.
By then, Ho source company will increase sales revenue of 4 billion yuan, profits and taxes 420 million yuan, to achieve gorgeous upgrade transformation.
The park project is being installed