The two phase of the project space furnace project is working overtime to catch up
Source:Director Office   Author:Wang Xiaoyu   Time:2013-10-26   Read:930second  

 

 

Following the space furnace project successfully drove after the operation, the two phase of the project in 2013 August formally installed. The two phase of the project space furnace project design capacity of 180000 tons of synthetic ammonia, the project with the same phase process, using the most advanced with independent intellectual property rights of the aerospace furnace pulverized coal gasification technology, has a high degree of automation, low consumption, low cost, compared with the old process of synthetic ammonia, each year for the company production cost savings of nearly forty million yuan.

The weather is good, it is the construction of the golden age. The two phase of the project space furnace project has entered the installation of piping, the peak, into the construction site, everywhere is a busy scene be in full swing. Time was tight, the task is heavy, the construction site is in order. According to the official responsible for the project, the two phase of the project space furnace project and a project than there are still many differences. In order to better meet market demand, joined the methanol production equipment, the structure of the product can be adjusted according to market, in order to maximize the benefits. The design of the scheme are.

At present, the main process of two stage gasification section of pipeline engineering of aerospace furnace project matching has been completed, the instrument regulating valve installed, you can enter the blowing, pressure test, leak testing, commissioning phase. Air separation process of cold box, methanol washing section in the large tower, synthesis process equipment have been installed in place, and to complete the rectification work,, has completed 80% installation of pipeline. Aerospace furnace project the two phase of the project transformation section with the national first "warm water heat transfer" transformation process, compared with the ordinary process of this technology, has small system resistance, by-product steam quantity, reasonable utilization of heat and other advantages, this section of the construction has been completed, ongoing equipment installation, commissioning.

To speed up the progress, for several months, aerospace furnace project builders have braved the scorching summer heat work at the construction site; to speed up the progress of the project, they work overtime to install the machine every day. In order to solve a technical problem, they met to discuss the late into the night; in order to guarantee the project quality, the implementation scheme for the optimization, repeated demonstration. In everyone's tireless efforts, to ensure that the project by the time node smoothly.

In order to ensure the project quality, project of required materials, valves, internals are strict scrutiny, docking, weld, tower engineering pipeline leveling, correction and strict implementation of on-site supervision, Cengcengbaguan, has provided the powerful safeguard for the project quality.

In order to ensure the construction safety, extension office set up a special inspection group of safety production by the project leading group and section chief composition, real-time check, and construction of the parties together weekly summary report, inspection results, make the safety management in the control condition.

As a part of space furnace has entered a stage of normal production, most managers focus on the production and operation of first phase project of maintenance, the two phase of the project installation personnel shortage. In the face of difficulties, the staff of project department didn't be intimidated, but with a positive attitude to cope with the challenge. In the unified deployment project department leadership, take the multi patch management measures, although each employee's workload has increased greatly, but they work hard and perseveringly, carry forward the spirit of continuous fighting, seize the current favorable opportunity to project construction, do not suffer not tired, quietly working.

The two phase of the project space furnace project space division, gasification section is expected in December 2014 April car grid, the two phase of the project will be completed and put into operation, will be the new annual production capacity of 180000 tons of synthetic ammonia, new sales income of about 432000000 yuan.

 

 

CONTACT US

Anhui Province, Fuyang City, Fukang Road No. 1

0558-2368015 2368080

haoyuanweb@163.com

皖公网安备 34120002001531号

Message:
Name:
Telephone:
mailbox:
Technology supporter: Haoyuan Group Information Center
Technology supporter: Haoyuan Group Information Center
T
O
P