November 23, 3 # urea plant Full stop checks, maintenance.
The planned inspection, maintenance for a period of fifteen days, is planned for high-voltage equipment into the ring detection, while also restricting device to solve the bottleneck problem of production. For example, the replacement of the belt conveyor belt, replace flash cold, replacing the desorption tower outlet pipes, cleaning up the evaporator condensate, transformation distillation column, rinse the heat exchanger, the interface is reserved for lithium bromide devices. The special equipment to detect invite testing authority - Nanjing Special Inspection Institute for High Pressure ring for testing. Repair work done to check and repair not stay dead.
By 3 # urea plant inspection and maintenance, to ensure safe and stable operation of the device, as well as the summer next year fully prepared.